Client: Gabrovo Municipality
Funding by: Operational Programme Environment 2007-2013
Term: 2013 – 2015
Terms of Contract: Design, Designer Supervision, Commissioning and Staff Training
Project Background:
The project involved the expansion, reconstruction and modernisation of WWTP Provadia, which was outdated and physically obsolete. In view of the higher requirements of the recipient and the higher water volumes, a new technological design was selected. The plant is an element of a programme for design of urban waste water treatment plants for towns with a population equivalent of over 10,000 under Operational Programme Environment and was designed for a population equivalent of 99 780 and Qav/day =18 505 m3/day.
The site was commissioned in 2015.
Project Activities:
BORA elaborated the entire working design for all parts, carried out designer supervision during the construction works, trained the staff of the plant, prepared operating instructions and supported the testing and commissioning of the new WWTP.
>> View all projects